Road near Santiago to be reconstructed

CSAH 16 will be reconstructed as a rural section roadway having 2-12’ thru lanes, 6’ paved shoulders and right turn and bypass lanes at major intersections.

It is the county’s intent to begin work on June 11, 2012, and have all work completed by September 28, 2012. The detour will be going up on Monday, June 11, 2012.

The contractor will begin milling up the existing asphalt on Monday, June 11. By midweek they will begin shoulder widening and ditch grading. Check the website for future updates.

Construction detour

The reconstruction will require that CSAH 16 be closed to thru traffic and detoured for the duration of the project.

The detour will utilize CSAH 6, CR 48 and CSAH 11. Please see the Sherburne County website for detour map.